Lesson 2: Overseeing Plans and Schedules
The Project Figures report returns "As of the Moment" project metrics for a
given project to all its WBS levels.
a) True
b) False
Which predecessor/successor relationship is described in this statement:
Task B can't finish until Task A is done. They don't have to end at the same
time. Task B can end any time after Task A ends.
a) FS (Finish-to-Start)
b) SS (Start-to-Start)
c) FF (Finish-to-Finish)
d) SF (Start-to-Finish)
When using the Desktop Resource Scheduler, which tab contains a “heat
map” to warn of overscheduling?
a) Project
b) Employee
c) Schedule
d) Filters