Page 41 - GC_Proj_Plan_Participant_GuideSDL
P. 41

LESSON 4: USING PLAN SETS



               Learning Objectives
               Create and manage the plan sets and versions available on a project
                   •  Create one or more baseline plans for a project
                   •  Use multiple plan sets to manage various planning scenarios


               Introduction

               Included in Unanet’s Project Portfolio license, the Plan Set feature provides functionality
               to manage various planning scenarios and/or the ability to create baseline plans by
               creating one or many "sets" of plans, grouped together in what is referred to as a Plan
               Set. Both People plans and Expense plans may be associated with a particular version
               of a "plan set".


               Creating and Managing Plan Sets

               A project can have one to many plan sets, and one to many versions within each
               distinct plan set name. The Manage Plan Sets menu option is only visible once the
               feature has been enabled in Properties > Forecasting > General. Users with the
               Administrator or P&R Administrator role can define the set of Plan Set Names available
               for use in Admin > Setup, while users with the Project Manager role can manage the
               plan sets on their current projects. All Project-level planning-related screens will allow
               for the designation of the desired plan set to which a particular plan should belong
               (including all planning screens and the project planning grids). The ability to lock all
               plans in a plan set can be accomplished on an individual project via the Plan Sets
               option in the left side menu or across multiple projects via the Forecast > Manage Plan
               Sets > Lock Plan Sets screen. Several reports, including the Plan Set
               Comparison and Plan Set Version Comparison, are available to compare various plan
               sets and versions of those plan sets.

                          Demo 4.1 – Configuring Plan Sets
                          Review the system requirements to enable and manage plan sets, then
                          discuss the process of assigning one or more plan sets to one or more
                          projects.


               Demo Steps

                   1.  Explain the Properties related to using plan sets.
                   2.  Discuss recommendations for creating Plan Set Names.
                   3.  Compare the assignment of plan sets using the Forecast > Manage Plan Sets
                       menu options with using the project-level Plan Sets left-side menu option.




               LESSON 4: Using Plan Sets
                                                                                  ©2022 Unanet. All rights reserved.   41