Page 30 - Unanet GovCon: Managing Project Execution and Control - Participant Guide (ILT)
P. 30

6.  On the row for the user “Harriette Anderson”, select the three-dot menu and
                       select Swap Person.
                   7.  In the Swap Person window, select “Gerald Jefferson” and press Apply.
                   8.  In the row for the user “Henry Douglas”, select the cell JUL-16 and add 20
                       hours.
                   9.  Press Save Assignment.

               Part 3: Re-run the metric reports to review the impact of the changes
                   1.  Navigate to Reports > Dashboard > Project Accounting.
                   2.  In the Summary Reports column, select the report “Project Revenue & Funding
                       Summary” and modify the report criteria as indicated below:

                    REPORT ON:                      All Projects I can see

                    PROJECT:                        CS-GOV-CON – 253CONSULT PM3-FORECAST-TM

                    DATE RANGE:                     6/15/2024 to 12/31/2024


                                                    Include Actuals and Assignments for Active Plan Sets
                    FORECAST OPTIONS:               5/31/2024 Use Actuals Through Date

                                                    Calculate remaining plan/budget based on:
                                                      Remaining hours/expenses per work day

                                                     Using Line Item Date within range
                    INCLUDE EXPENSE REPORTS:          Include non-completed Expense Reports
                   3.  Press Run Report.

               Part 4: Create a Project Note to document the project review

                   1.  Navigate to Contracts > Project > List.
                   2.  On the Search tab, use the Project Org. Code field to view all “253CONSULT”
                       projects.
                   3.  Open the List tab and select the edit icon for the project “253CONSULT PM3-
                       FORECAST-TM”.
                   4.  In the project menu, select Notes.
                   5.  Press the Add Project Note button and enter the data shown below:


                    ADD NOTE FOR 253CONSULT PM3-FORECAST-TM:

                    Note Title:         June 2024 Project Review
                                        Completed review; swapped Design Engineer for a more senior engineer to
                                        solve ongoing design issues; increased hours needed for System Engineer.
                                        Impact to revenue has created a greater negative funding situation; need to
                    Note Description:   review ways to complete project within available funding or request more
                                        funding. Additionally, the new engineer added to the project has reduced
                                        profit by a significant amount.





               LESSON 3: MONITORING AND CONTROLLING PROJECT PEFORMANCE
                                                                                  ©2022 Unanet. All rights reserved.   30