does not mean that user is actually available to perform the work.  As such, the People
               Resource Allocation Report can be used to help identify which user has both the skills
               needed and availability based on plans or assignments on other projects.

                        Be aware that overlapping assignments are not allowed. If trying to swap a
                        user’s hours and the receiving user does not show as an option, the receiving
                        user already has an existing plan for that period of time.



               Shift Left/Right

               Once plans and assignments have been created, they can be moved to different time
               periods. This is called ‘Shifting Left/Right’.  It is the functionality to move the contents of
               a row of cells X number of cells to the right or left. This is only available when using a
               grid view of the plan/assignment.

               When the populated cell moves to a new period all values in the cell, as well as any
               override values associated with the cell will be moved.  This feature may be helpful, for
               example, if you need to delay a project for one or several months and would like to shift
               existing entries without having to re-key them in.

               The controls involved in this functionality include the leading check box on each row, the
               Shift Left and Shift Right buttons, as well as the Number of Periods entry field.  Note
               that you can check the check box at the very top of the grid which acts as a toggle to
               check / uncheck all available check boxes in the grid.

               Click Shift Left or Shift Right depending on the direction you would like to move the
               plans. Note that you cannot shift plans outside of the time periods displayed in the
               planning grid.


               Revise Future Assignments

               When reforecasting a project, you may decide to simply adjust hours and/or labor
               categories to ensure you can complete the project.  The key takeaway for adjusting
               hours/labor categories is to only adjust the future periods as there is little need to
               update past assignments.  This is because reports offer the criteria to show hours
               through a specific date and then remaining assignments.  Actuals will always replace
               prior assignments.