Page 50 - Participant Guide - Unanet GovCon Analyzing Project Metrics
        P. 50
     LESSON 6:  CONTROLLING PROJECT PERFORMANCE
               Learning Objectives
                   •  Determine corrective action
                   •  Reforecast project labor or expense in future periods
                          o  Confirm adjustments meet approved revenue and profitability metrics
               Introduction
               One of the recommendations to help monitor a project’s progress is to determine any
               corrective actions. Three viable options to correct a project that is not meeting the
               metric thresholds are explained in more detail below.
               Corrective Action (Do Nothing)
               There are a few common reasons to do nothing despite a particular project or task
               exceeding the monitoring thresholds for one or more of the corporate KPIs.
                       Tour 6.1 – When and How to Do Nothing
                       Instructor is logged in as Gus Lead. His relevant role is Project Lead. A Project
                       Manager can also perform these recommended steps.
               Tour Highlights
                   -  Review how to add a project note and emphasis use of relevant note types.
               Lesson 6:  Controlling Project Performance
                                                                              ©2020 Unanet. All rights reserved.     49





