Corrective Action (Rebaseline)

               The concept of rebaselining a project includes a conscious rework of the project plan
               because the current plan is no longer valid. Recall, a valid plan requires that the active
               plan meets the following elements:























               The project team may evaluate the project’s current and forecasted performance and
               determine that the existing plan is no longer valid. Under this circumstance, they may
               decide to rebaseline, Unanet offers a feature called Multiple Plan Sets that easily
               supports this decision.

               Multiple Plans Sets
               Unanet supports the use of multiple Plan Sets for the purpose of more complex
               planning of labor and expenses. Examples of using Plan Sets include Reforecasting,
               Corporate Budgeting and Scenario Planning.


                         There is a property setting than can provide a Project Lead access to the plan
                         set functionality and several reports that use multiple plan sets



















               Lesson 6:  Controlling Project Performance