Periodic Performance Reviews
               As mentioned in the Planning Phase, it is common that the executive team of a
               company will have specific targets for revenue and profitability for all phases of the
               project’s lifecycle. In Unanet, the project teams can use the same key reports to analyze
               the project’s ongoing performance as we used for planning the projects by simply
               changing a few of the criteria settings.

               The table below helps explain a simple cross tab approach to which report and which
               fields are relevant based on the billing type of the project/task. This table represents
               evaluation of the reports by using a ‘forecasted’ set of criteria. Forecasted, in Unanet
               terms, is the total sum of project actuals plus the remaining people assignments and/or
               expense budgets.

                                                                                                Time and
                                                     Cost-Plus              Fixed Price
                                                                                                Materials
                    Revenue Remaining
                           Funded                 Within corporate         Depends on
                 Funded Value – (Actuals +           thresholds           Billing schedule     Exactly zero
                    Future Assignments)

                                    Report: Project Revenue & Funding Summary
                         (filtered on Actuals + Future People Assignments or Expense Budgets)

                         Profitability
                    (Net Revenue / (Net                                                           Within
                                                         N/A
                   Revenue / (Revenue of         (Contract-defined)      Within corporate       corporate
                                                                            thresholds
                      Actuals + Future                                                          thresholds
                        Assignments)

                                       Report: Periodic Cost Summary & Status
                         (filtered on Actuals + Future People Assignments or Expense Budgets)



               This upcoming section will highlight report criteria to prepare for the monitor and control
               phase. Specifically, this version of each report will focus on a ‘forecasted’ view of the
               underlying data. A forecasted view of the revenue includes the actuals through some
               period of time, typically, prior timesheet, billing, or closing period, and future
               assignments/budgets. This view reflects what charges are expected in the future
               periods.

                       While a forecasted view could include actuals through a particular date plus
                       future plans, such configuration will require you separately control the people
                       assignments because the assignments are the only area that you can control
                       number of hours charged on a project or task.