Page 57 - Participant Guide - Unanet GovCon Analyzing Project Metrics
P. 57

Activity 6.4 – Reforecasting APF-FORECAST-TM

                       Read through the metric and technical reviews, the results of his research in
                       Unanet and the corrective actions he will perform in the next activity.
                       If you want, you can run the saved reports that Gus would have run to increase
                       your awareness of using system reports to prepare for a project reforecast.

                       Use the Activity Steps to reforecast a project and then reevaluate the key
                       metrics.
                       Stay logged in as Gus Lead. userid: glead  password: welcome

               METRIC REVIEW:

                   -  The corporate thresholds for this project:


















                   -  Report results revealed the following:
                       -  Revenue & Funding Summary Report on forecast of actual + remaining
                          assignments shows remaining funded is negative more than the $300
                          corporate threshold

                              Saved Report: Activity 6.4-Revenue Metric APF-FORECAST-TM
                       -  Cost Summary & Status Report on forecast of actuals + remaining
                          assignments shows that Forecasted Profit is within the 2% threshold

                              Saved Report: Activity 6.4-Profit Metric APF-FORECAST-TM
               TECHNICAL REVIEW: Gus reviewed the project notes and held a meeting with the
               team. He decides to make the following changes.

                          1.  Replace the current Design Engineer (Harriette) with someone more
                              experienced in solving the design issues identified by the team.
                          2.  Due to the technical issues, several team members worked some
                              overtime. The Sys Engineer needs 20 more hours next month to help
                              resolve the issues.





               Lesson 6:  Controlling Project Performance
                                                                              ©2020 Unanet. All rights reserved.     56