Page 58 - Participant Guide - Unanet GovCon Analyzing Project Metrics
P. 58

RESEARCH COMPLETED:

                   -  Performance Reports:  The Project Lead, Gus, ran Performance Reports for the
                       last month (5/1 – 5/31). The reports showed that the current Design Engineer is
                       Harriette, the System Engineer is Henry, and showed the variance between
                       assignments and actuals.

                              Saved Report: APF-Activity 6.4-Person Performance Report    or
                                              APF-Activity 6.4-Project Performance Report

                   -  Skills Reports:  Gus also ran a Person Skills Report and found that Hercules
                       has the same types of skills as Harriette; however, his skills proficiency is
                       significantly higher that Harriette. The project team assumes Hercules may have
                       a higher salary than Harriette.
                              Saved Report: APF-Activity 6.4-Skill Profile-Harriette’s Skills

                                              APF-Activity 6.4-Skill Profile-Harriette's Replacement

                   -  Resource Allocation Reports:  Gus then runs People Resource Allocation
                       Report to find that Hercules is not currently assigned to a Billable project

                              Saved Report: APF-Activity 6.4-Resource Allocation (on
                              Assignments)

                       He also ran a modified version of the report to see if Hercules is planned on an
                       effort to find that he is planned on a proposal project.
                              Saved Report: APF-Activity 6.4-Resource Allocation (on Plans)


               CORRECTIVE ACTIONS DETERMINED:

                   COA 1. Move Harriette’s remaining assignments to Hercules starting June 16
                                                                                                     th
                   COA 2. Increase Henry’s project assignments by 20 hours for July
                   COA 3. Run metric reports to evaluate impact to profitability and remaining revenue

                   COA 4. Prepare a project note and assign it to Fay Contracts





















               Lesson 6:  Controlling Project Performance
                                                                              ©2020 Unanet. All rights reserved.     57