c)  Due to the Bill date on the billing schedule - This is an incorrect answer
                                 because a billings schedule with a Bill date is used for Fixed Price
                                 contracts

                          13. How is Deferred Revenue, for the Billing Type CP (Cost Plus) projects,
                              handled at the end of the year?
                              a)  Deferred Revenue cannot exist for CP (Cost Plus) projects - This is an
                                 incorrect answer because Deferred Revenue could exist if the indirect
                                 rate used to calculate Billings and Revenue are not the same
                              b)  Corrected through a “true-up” invoice or journal entry since
                                 Actual rates are often unknown until after the year end close -
                                 This is the correct answer because CP projects should be reconciled
                                 once Actual rates are known
                              c)  Not Corrected since Actual rates are often unknown until after the year
                                 end close - This is an incorrect answer because CP projects should be
                                 reconciled once Actual rates are known

                          14. What drives when a fixed price item is included in the Billing & Revenue
                              Post?
                              a)  Bill date in the Project level Billing menu - This is the correct -
                                 because the bill date drives when amounts are included in the B&R
                                 Post
                              b)  When timesheets are in a Lock/Extracted status - This is the incorrect
                                 answer because this is the driver for TM/CP projects
                              c)  When expense reports are in a Lock/Extracted status - This is the
                                 incorrect answer because this is the driver for TM/CP projects

                          15. When setting up the Project level Billing for Fixed Price Projects (FP),
                              what are the Revenue Recognition Method choices available to be used to
                              determine when Revenue is recognized?
                              a)  Custom Schedule is the only Revenue Recognition Method used for
                                 FP projects - This is an incorrect answer because the revenue
                                 recognition methods are Custom Schedule, % Complete, When Billed
                                 selected for FP projects
                              b)  Revenue recognition methods are not selected for FP projects - This is
                                 an incorrect answer because revenue recognition methods are
                                 selected for FP projects
                              c)  Custom Schedule, % Complete, When Billed - This is the correct
                                 answer because these are the selectable revenue recognition methods
                                 for FP projects