Corrective Action: Rebaseline
When a project plan is no longer valid, it may be necessary to rework the plan in a
process called rebaselining in which existing plans, assignments, and budgets are
modified to ensure accurate reporting. For an active plan to be considered valid, it must
meet the following criteria:
Occurs within Profit Rate is Plans all
the Period of within corporate revenue in the
Performance thresholds contract
Adheres to Technically
contract executable
compliance
The project team may evaluate a project’s current and forecasted performance,
determine that the existing plan is no longer valid based on these guidelines, and
decide to rebaseline the project plans. The Multiple Plan Set feature supports more
complex planning of labor and expenses, including reforecasting, corporate budgeting,
and scenario planning. Plan Sets are discussed in greater detail in the course Unanet
GovCon: Planning Project Resources.
Tour 3.3 – Creating a Revised Plan (Rebaselining)
Log in as the Administrator, Fran Schaeffer (fschaeffer/welcome) to enable the
use of multiple plan sets and generate plan set comparison reports.
Tour Highlights
• Review use cases for multiple plan sets
• Modify plans and update future assignments and budgets