Page 16 - Participant Guide - Unanet GovCon Managing Project Resources
P. 16

People to plan: Filter by last name or Person Organization code, default labor
               category, location, and/or skills.

               Display Options: These are helpful to display information such as dates and budgets
               from the project or task on the grid.


               Tips for adding and editing people plans in a planning grid

               There are several double-click features to quickly update many planning periods at the
               same time.

               For example, use a double click on each of these areas in the grid:
                   1)  On the Person’s name: this opens an edit screen to update all planning periods
                       for this one person
                   2)  On one single planning cell:  this opens the edit screen to update this one
                       increment for this one person
                   3)  Double clicking into one column header edits all users in the grid for that one
                       increment
                   4)  Finally, double clicking on the top left corner of a grid opens the edit screen for all
                       users and all increments in the entire grid

               The grid entries have many features. Some include task selection, hours or utilization,
               which bill rates and cost rates to use, swapping plans to a different person and a myriad
               of fields that can be derived by the system based on your project setup. While there are
               many features in the grid, below are some of the most common project management
               recommendations.

               Bill Rate
               Recommendation is to allow the bill rates to derive directly from the project level labor
               category setup. This ensures that any escalation rates are used in the appropriate
               period.

               Cost Rate
               Recommendation is to have the cost rate derive from the person’s profile. Again, this
               ensures that any escalation rates are used in the appropriate period. However, it may
               be logical to override the cost rate if planning records are using either TBD resource or
               maybe a fixed cost rate for a subcontractor.

               Cost Element
               The cost element can be derived from the person’s profile rate information. It is
               recommended to allow the system to derive the cost element as this field is time bound
               on the cost rate record in the person’s profile and would always provide the correct cost
               rate based on the date.





               Lesson 2: People and Expense Plans
                                                                              ©2020 Unanet. All rights reserved.     15