Part 3: Use the skills learned in class to create people plans for the following users:
1. Plan UU User00, Amara
a. Double click on the row for Amara
b. In the PLAN LABOR section, check the box Enable Budget field for
updates and enter 80 hours
c. In the MISCELLANEOUS section > Labor Category field, select UU
APSTAR Business System Analyst
d. Click Save to return to the grid and review the results
2. Plan UU User00, Jack
st
a. Double click the 1 monthly increment cell for Jack
b. In the PLAN LABOR section enter 80 hours
c. In the MISCELLANEOUS section > Labor Category field, select UU
APSTAR Business System Analyst
d. Click Save to return to the grid and review the results
3. Move Jack’s hours to the right by 2 months
a. Check the box on Jack’s row
b. Enter 2 for the Number of periods to shift selected items left or right
c. Click the Shift Right button
4. Plan UU User 00, Milo
st
a. Do not use the double click. Instead, simply enter 40 hours in the 1
month. This will result in the labor category deriving a result on its own.
5. Click Save