PART 4: Review and analyze the report results for forecasted revenue
                       1.  In TOTAL section on the far-right end of the report, note the following results
                       •  REMAINING FUNDED:
                          -  if the value is positive, this indicates the calculated revenue is LESS than
                              the total of the Funded Value field.
                                 -  This represents a missed opportunity to capture revenue.
















                          -  if the value is (negative), this indicates the calculated revenue is MORE
                              than the total of the Funded Value field.
                                     -  This represents the potential for overspending the project and
                                     could put the project ‘at-risk’ if allowed to continue with this
                                     forecast.