PART 4: Review and analyze the report results for forecasted revenue
1. In TOTAL section on the far-right end of the report, note the following results
• REMAINING FUNDED:
- if the value is positive, this indicates the calculated revenue is LESS than
the total of the Funded Value field.
- This represents a missed opportunity to capture revenue.
- if the value is (negative), this indicates the calculated revenue is MORE
than the total of the Funded Value field.
- This represents the potential for overspending the project and
could put the project ‘at-risk’ if allowed to continue with this
forecast.
Lesson 3: Revenue and Profitability Reports
©2020 Unanet. All rights reserved. 23