Page 47 - Unanet AE: Using Project Management
P. 47

Grid Descriptions
                   •  Index - Index of the project node, primarily used for assigning predecessors (see
                       below).
                   •  WBS - Project Path (read only).
                   •  Name - Project Name (read only).
                   •  Duration - Increase or decrease the amount of time allotted to a project node in
                       increments of days or weeks (based on the selected view option). This updates
                       associated finish dates and Gantt Bars. Project level duration is summarized and
                       reflected in the number of planned days, start to finish.
                   •  Start - Planned start date.
                   •  Finish - Planned end date.
                   •  Predecessors - Indicated by the Index number, predecessors allows you to
                       control, for instance, the schedules for a list of tasks underneath a project phase.
                       Using a predecessor, you can effectively lock the schedules of a WBS together.
                       Rescheduling the predecessor has a ripple effect on the schedules of the linked
                       nodes.

                       The nature of the relationship between a predecessor task and a successor task
                       determines the type of task dependency to use. This relationship can be defined
                       by typing the following codes into the Predecessors column prefixed by the Index
                       ID (e.g., 2FS):

                          o  FS (Finish-to-Start) - Task A must finish before Task B can start. This is
                              very commonly used and the default dependency created if only an Index
                              ID is entered into the Predecessors column.
                          o  SS (Start-to-Start) - Task B can't start until Task A starts. Task B can
                              begin any time after Task A begins. This method can be beneficial as it
                              can help reduce the overall duration of the project as it allows for task
                              overlap.
                          o  FF (Finish-to-Finish) - Task B can't finish until Task A is done. They don't
                              have to end at the same time. Task B can end any time after Task A ends.
                              Similar to SS, FF dependencies can also reduce the overall duration of a
                              project.
                          o  SF (Start-to-Finish) - Task B cannot finish until the start of Task A. This is
                              a very rare scenario of Task in any type of project.
               Chart
               The chart is reactive to the view options and the WBS Grid settings and displays two
               types of bars: Gantt bars and a Summary bar.







                                                                            ©2024 Unanet. All rights reserved.  47
   42   43   44   45   46   47   48   49   50   51   52