Page 48 - Unanet AE: Using Project Management
P. 48
Gantt Bars
Gantt bars (blue) reflect the settings of the associated project node listed in the WBS
chart. Gantt Bars can be moved by editing the WBS chart or by clicking and dragging
the Gantt bar. This will adjust any associated schedules. You can alter the duration (and
subsequently start and end dates) of a task by gripping the left or right edge of the Gantt
bar and increasing or decreasing its length.
Summary Bar
The summary bar shows a running total of the time represented by all scheduled tasks.
While Gantt bars can be edited, the Summary bar is Read Only.
Other Options
• Print - Launches print preview for content of the Gantt Chart and WBS Grid.
• Automatically move Schedules with Start Date - When checked, Start Dates
are impacted when sliding Gantt Bars.
• Save - Saves Gantt information.
• Save & Close - Saves Gantt information and closes the Gantt window.
• Close - Closes the Gantt window without saving.
Activity 2.1 – Work with a Gantt Chart
In this activity, you will work with a Gantt chart.
Activity Steps
Desktop
Part 1: Input Task Duration
1. Navigate to Project Management > Project Planning. The Project Planning
applet opens.
2. Type PN0005 in the Code field.
3. Press Enter. The Project Planning applet populates with information for New
Building.
4. Select the Gantt button in the toolbar. The Gantt window opens.
5. Use the information in the table below to add the WBS information.
Phase Task Duration
Schematic Design Civil 3 weeks
Schematic Design Electrical 3 weeks
Schematic Design Mechanical 3 weeks
©2024 Unanet. All rights reserved. 48