Page 56 - Unanet AE: Using Project Management
P. 56

Check Your Understanding


                          The Project Figures report returns "As of the Moment" project metrics for a
                          given project to all its WBS levels.

                                 a)  True
                                 b)  False



                          Which predecessor/successor relationship is described in this statement:
                          Task B can't finish until Task A is done. They don't have to end at the same
                          time. Task B can end any time after Task A ends.

                                 a)  FS (Finish-to-Start)
                                 b)  SS (Start-to-Start)
                                 c)  FF (Finish-to-Finish)
                                 d)  SF (Start-to-Finish)



                          When using the Desktop Resource Scheduler, which tab contains a “heat
                          map” to warn of overscheduling?

                                 a)  Project
                                 b)  Employee
                                 c)  Schedule
                                 d)  Filters





                          Refer to Appendix A for answers to the Check Your Understanding questions.















                                                                            ©2024 Unanet. All rights reserved.  56
   51   52   53   54   55   56   57   58   59   60   61