Page 30 - Unanet AE: Using Project Management
P. 30

Web
                   1.  Select Project Central. The Projects applet opens.
                   2.  Select the Plans tab.
                   3.  Select the New Building 2 project.
                   4.  Select the Gantt tab.
                   5.  Select the Predecessors cell for Schematic Design / Index 3 line. The
                       Schematic Design Information window opens.
                   6.  Select the Add button. Note: You will need to click the Add button multiple times
                       to view the additional lines for the other phases.
                   7.  Select the 2 – Pre-Design (PN0006-001) check box.
                   8.  Select the Save button.
                   9.  Use the information in the table below to assign predecessors to other phases in
                       the project.

                                     Phase                            Predecessor                Index #

                        Design Development                  Schematic Design                     3
                        (Index line 4)

                        Construction Documents              Design Development                   4
                        (Index Line 5)

                        Bidding/Negotiations                Construction Documents               5
                        (Index line 6)

                        Construction Administration         Bidding / Negotiations               6
                         (Index line 7)


                   10. Type 50 in the Duration column for the following phases:

                          •  Pre-Design
                          •  Schematic Design
                          •  Design Development
                          •  Construction Documents
                          •  Bidding/Negotiations
                          •  Construction Administration
                   11. Select the Save button for the project.


               Basic Budget Setup

               Unanet AE allows users to create project budgets using multiple methods. Budgets can
               be defined as explicit unit/hour and dollar values keyed into associated budget fields, or
               with the Project Rollup feature, the software can calculate budget numbers based on
               the summation of allocations or resource schedules.



                                                                            ©2024 Unanet. All rights reserved.  30