Top-Down Budgeting: You can set the budget values at the project level and they will
               distribute to the lowest level on the WBS.
               Bottom-Up Budgeting: You can set the budget values at the lowest level and it will
               calculate up to the project level.

               Percentages: You can assign percentages to calculate out the distribution of Hours or
               Dollars identified at the project level. For Instance, if you enter a percentage into the
               Labor Hour % column at each of the lowest nodes and then populate Labor Budget
               Hours field at the parent level, the system will calculate the available Labor Budget
               Hours for each of the lowest nodes.

               When the lock icon is dark gray, you can enter percents in lower-level nodes. Click the
               lock icon to turn it to green, then enter a budget number at the parent level to have the
               numbers distributed based on the percentages. If you enter a number in a budget
               column on a lower level before setting the lock icon to green, the percentages will be
               overwritten to match the number distribution. When the lock icon is dark gray, numbers
               cannot be entered at the lower levels. The preceding applies to relationship between the
               columns Labor Budget Hours and Labor Hours %, Labor Budget Amount and
               Labor Amount %, ODC Budget Amount and ODC Amount %, ICC Budget Amount
               and ICC Amount %, and OCC Budget Amount and OCC Amount %.




                         Activity 1.8 – Set up a Basic Budget
                         In this activity, you will set up a basic budget in the Project Planning applet.

               Activity Steps

               Desktop
                   1.  Navigate to Project Management > Project Planning. The Project Planning
                       applet opens.
                   2.  Type PN0005 in the Code field.
                   3.  Press Enter. The Project Planning applet populates with information for New
                       Building.
                   4.  Use the information in the table below to add the budget. The data is
                       automatically saved.

                   •  Note: Select the – (minus) sign next to each phase to contract the lines for easier
                       text entry. This can be done for all nodes at a level by selecting the level under
                       the Show dropdown above the project grid.
                   •  Note: The column header labels shown are label override names used in this
                       particular training environment.