Page 63 - Unanet AE: Using Project Management
P. 63
6. Select the X to close the window.
7. Select Edit > Percent complete history. The Edit > Percent complete history
window opens.
8. Select Design Development.
9. Select the Add Row button.
10. Enter <A date that is 4 months after the date of the row above> in the Date cell.
11. Type 90 in the Labor % cell.
12. Select Construction Documents.
13. Select the Add Row button.
14. Enter <A date that is 1 month after the date of the row above> in the Date cell.
15. Type 65 in the Labor % cell.
16. Select the X to close the window.
17. Select Edit > Earned Value. The Earned value window opens.
18. Select Pre-Design.
19. Select the X to close the window.