Page 63 - Unanet AE: Using Project Management
P. 63

6.  Select the X to close the window.
                   7.  Select Edit > Percent complete history. The Edit > Percent complete history
                       window opens.
                   8.  Select Design Development.
                   9.  Select the Add Row button.
                   10. Enter <A date that is 4 months after the date of the row above> in the Date cell.
                   11. Type 90 in the Labor % cell.
                   12. Select Construction Documents.
                   13. Select the Add Row button.
                   14. Enter <A date that is 1 month after the date of the row above> in the Date cell.
                   15. Type 65 in the Labor % cell.
                   16. Select the X to close the window.
                   17. Select Edit > Earned Value. The Earned value window opens.
                   18. Select Pre-Design.
                   19. Select the X to close the window.